Owner / EPC | PLANT/PROJECT/LOCATION | Peak Manpower | Piping - MP | Structure / Equipment - MP | WORK CATEGORY / JOB DESCRIPTION | LOCATION | STARTED | COMPLETED |
EXXONMOBIL | FURNACE RECOIL WORK | 77 | 62 | 15 | FURNACE MAINTENANCE | JURONG ISLAND, SINGAPORE | Jun-2022 | Feb-2023 |
EXXONMOBIL | B286 - AER PROJECT | 31 | 28 | 3 | MECHANICAL & PIPING WORK | JURONG ISLAND, SINGAPORE | Dec-2018 | Dec-2019 |
EXXONMOBIL / MITSUI | AuroraEOS PROJECT | 160 | 128 | 32 | PIPING WORK -C80PR0004 PROJECT B ARR-ICR & FINISHING PIPING PACKAGE | JURONG ISLAND, SINGAPORE | Dec-2015 | Aug-2017 |
EXXONMOBIL / MITSUI | AuroraEOS PROJECT | 160 | 128 | 32 | EQUIPMENT INSTALLATION -C80PR0003 PROJECT A | JURONG ISLAND, SINGAPORE | Jul-2015 | Aug-2017 |
EXXONMOBIL | TRANSPORTATION & MECHANICAL ERECTION | 36 | 32 | 4 | HEAVY EQUIPMENT WORKS | JURONG ISLAND, SINGAPORE | Nov-2014 | Jan-2015 |
EXXONMOBIL | JURONG TURNAROUND PROJECT | 75 | 68 | 8 | MECHANICAL AND PIPING WORK | JURONG ISLAND, SINGAPORE | Sep-2014 | Nov-2014 |
EXXONMOBIL / STONE & WEBSTER | SINGAPORE PARALLEL TRAIN PROJECT (SPT) OLEFINS RECEOVERY AND UTILITIES FACILITIES | 89 | 71 | 18 | STRUCTURAL STEEL TO COMPRESSOR SHELTERS | JURONG ISLAND, SINGAPORE | Mar-2012 | Mar-2013 |
EXXONMOBIL / STONE & WEBSTER | SINGAPORE PARALLEL TRAIN PROJECT (SPT) | 9 | 8 | 1 | STRUCTURAL STEEL TO COMPRESSOR SHELTERS | JURONG ISLAND, SINGAPORE | May-2010 | Mar-2012 |
EXXONMOBIL / MITSUI | SINGAPORE METALLOCENE ELASTOMERS (SME) | 66 | 56 | 10 | EQUIPMENT INSTALLATION WORKS | JURONG ISLAND, SINGAPORE | Sep-2009 | Nov-2010 |
EXXONMOBIL / MITSUI | SINGAPORE POLYPROPYLENE (SPP2) PROJECT | 12 | 10 | 2 | EQUIPMENT INSTALLATION WORKS | JURONG ISLAND, SINGAPORE | Feb-2009 | Aug-2010 |